Farine Elementary School
$58M
Led closeout, and with the other project engineer, overhauled the punch process.
of closeout complete after six weeks, up from 20%
- closeout submittals, the bulk handled by me
- 218
- closeout submittals, the bulk handled by me, across 63 subcontractors
- punch list items created and tracked to completion
- 1,000+
- punch list items created and tracked to completion, co-led with one other project engineer