What I was responsible for
Led closeout
20% → 80%
Took closeout from 20% to 80% complete in six weeks, handling the bulk of the job's 218 closeout submittals across 63 subcontractors. Verified each one against the spec, and stayed on top of follow-up and coordination so every sub got theirs in on time.
Closeout went from 20% to 80% complete in six weeks. Systematized the punch process
1,000+
With the other project engineer, ran our own completion list and then a pre-punch before the architect arrived, with everything attached to each item, to save the architect and us time. Then built the punch list and worked more than 1,000 items to completion.
Coordinated attic stock deliveries
Took stock of each delivery as it arrived.
Helped schedule O&M training
Walked the site daily
Kept a current picture of everything going on across the job.