What I was responsible for
Coordinated subcontractors in the field
Checked in with foremen on when open schedule items would be finished, followed up on the dates they promised, and cleared the day-to-day blockers that would have held up the work.
Ran weekly 360-degree camera walks
The walks recorded progress and site condition week by week.
Built the initial punch list
Created it alongside my team and the architect.
Drove closeout with every subcontractor
Stayed on top of each sub so closeout documents came in on time, and made sure payment was held for anyone who hadn't submitted by substantial completion.
Checked closeout against the spec
Verified each closeout submittal for compliance with the spec, and helped coordinate attic stock deliveries.